Don’t get caught napping with a time-bar clause in your construction contract

Clients are often surprised when they discover clauses in their construction contract that requires them to give notice to the building contractor, usually within very short periods of time, of their intention to dispute a set of circumstances, failing which, they lose their right to refer such a dispute for dispute resolution. This then raises the question of why these clauses are present and how enforceable they are.

Interestingly, shortened time-based limits for the notification and resolution of disputes have become the norm in construction contracts. These clauses often referred to as “time-bar” clauses have found their way into the construction environment as a result of the following factors:

Tight time frames are generally imposed on contractors to finalize projects, with any delay potentially having a tremendous impact on the overall ability to complete on time.
The high risk of incurring damages and losses if a project is not completed on time, especially if the project is expected to generate revenue once completed or completion payments are delayed.
The high cost of having contractors and workers on-site without construction work proceeding.
In short, these clauses have become relevant to avoid excessive project delays flowing from unresolved disputes, as the longer a dispute takes to get resolved, the greater the cost to have the project eventually completed.

Most standardised, widely used construction contracts make provision for alternative dispute resolution forums, subject to these time-bar clauses outside of the traditional “court-based” litigation. Examples of such standardised forms include the NEC, FIDIC, JBCC and GCC forms of contract. The particular contract and its specific negotiated terms will of course need to be considered in every separate instance to determine the exact time limits imposed.

The NEC3 form of contract, for example generally requires that a party to the contract that intends to dispute any circumstance arising from the contract must within two to four weeks of becoming aware of the dispute give notice to the other party that it intends to do so. In certain instances, the time frames may be even shorter than this.

There has been considerable discussion regarding whether it is reasonable and whether it should be permissible to include such limitations in agreements. Our Constitutional Court in Barkhuizen v Napier in 2007 finally determined that subject to certain requirements, time-bar clauses are enforceable. They must however provide reasonable and clear notice periods.

So, given that these time-bar clauses are enforceable, care should be taken when concluding a construction contract so that these provisions and their parameters are understood and appreciated. If necessary, consider involving a construction or commercial attorney to help provide clarity on these provisions and guide you on how to successfully ensure that any dispute is timeously raised and correctly dealt with contractually.

LISTEN: Interview with Herman du Randt on the OFM Business Hour

Disclaimer: This article is the personal opinion/view of the author(s) and is not necessarily that of the firm. The content is provided for information only and should not be seen as an exact or complete exposition of the law. Accordingly, no reliance should be placed on the content for any reason whatsoever and no action should be taken on the basis thereof unless its application and accuracy have been confirmed by a legal advisor. The firm and author(s) cannot be held liable for any prejudice or damage resulting from action taken on the basis of this content without further written confirmation by the author(s).

February 28, 2023
Storm warning for accountable institutions without an updated RMCP

Storm warning for accountable institutions without an updated RMCP

The storm has passed—but the damage may be just beginning. With the 12 March 2025 deadline for submitting updated RMCPs now behind us, accountable institutions that failed to comply could be in the FIC’s crosshairs. This is more than a missed admin task—it’s a warning that the FIC is watching, and non-compliance could carry real consequences as South Africa continues its battle to escape grey listing.

Do you need to register as a credit provider? Here’s when and how

Do you need to register as a credit provider? Here’s when and how

Thinking of granting credit, even just once? You might be surprised to learn that doing so—even for as little as R1—could trigger a legal requirement to register as a credit provider. With recent changes lowering the registration threshold to zero, understanding when and how to register is more important than ever. Whether you’re a business or an individual, here’s what you need to know before issuing credit in South Africa.

Sign up to our newsletter

Pin It on Pinterest