Don’t get caught napping with a time-bar clause in your construction contract

Clients are often surprised when they discover clauses in their construction contract that requires them to give notice to the building contractor, usually within very short periods of time, of their intention to dispute a set of circumstances, failing which, they lose their right to refer such a dispute for dispute resolution. This then raises the question of why these clauses are present and how enforceable they are.

Interestingly, shortened time-based limits for the notification and resolution of disputes have become the norm in construction contracts. These clauses often referred to as “time-bar” clauses have found their way into the construction environment as a result of the following factors:

Tight time frames are generally imposed on contractors to finalize projects, with any delay potentially having a tremendous impact on the overall ability to complete on time.
The high risk of incurring damages and losses if a project is not completed on time, especially if the project is expected to generate revenue once completed or completion payments are delayed.
The high cost of having contractors and workers on-site without construction work proceeding.
In short, these clauses have become relevant to avoid excessive project delays flowing from unresolved disputes, as the longer a dispute takes to get resolved, the greater the cost to have the project eventually completed.

Most standardised, widely used construction contracts make provision for alternative dispute resolution forums, subject to these time-bar clauses outside of the traditional “court-based” litigation. Examples of such standardised forms include the NEC, FIDIC, JBCC and GCC forms of contract. The particular contract and its specific negotiated terms will of course need to be considered in every separate instance to determine the exact time limits imposed.

The NEC3 form of contract, for example generally requires that a party to the contract that intends to dispute any circumstance arising from the contract must within two to four weeks of becoming aware of the dispute give notice to the other party that it intends to do so. In certain instances, the time frames may be even shorter than this.

There has been considerable discussion regarding whether it is reasonable and whether it should be permissible to include such limitations in agreements. Our Constitutional Court in Barkhuizen v Napier in 2007 finally determined that subject to certain requirements, time-bar clauses are enforceable. They must however provide reasonable and clear notice periods.

So, given that these time-bar clauses are enforceable, care should be taken when concluding a construction contract so that these provisions and their parameters are understood and appreciated. If necessary, consider involving a construction or commercial attorney to help provide clarity on these provisions and guide you on how to successfully ensure that any dispute is timeously raised and correctly dealt with contractually.

LISTEN: Interview with Herman du Randt on the OFM Business Hour

Disclaimer: This article is the personal opinion/view of the author(s) and is not necessarily that of the firm. The content is provided for information only and should not be seen as an exact or complete exposition of the law. Accordingly, no reliance should be placed on the content for any reason whatsoever and no action should be taken on the basis thereof unless its application and accuracy have been confirmed by a legal advisor. The firm and author(s) cannot be held liable for any prejudice or damage resulting from action taken on the basis of this content without further written confirmation by the author(s).

February 28, 2023
Customary and Civil marriages are equal, says Constitutional Court

Customary and Civil marriages are equal, says Constitutional Court

The Constitutional Court has recently delivered a significant judgment reaffirming that customary marriages and civil marriages hold equal legal status. Importantly, the Court clarified the implications and validity of antenuptial contracts within the context of customary marriages.

CSOS or Court? The choice is yours

CSOS or Court? The choice is yours

The recent judgment in Parch Properties 72 (Pty) Ltd v Summervale Lifestyle Estate Owner’s Association and Others 2026 (1) SA 449 (SCA) (17 October 2025) has brought welcome clarity to the long‑standing question of whether the Community Schemes Ombud Service Act 9 of 2011 (CSOS Act) limits the jurisdiction of the High Court.

Hurt feelings ≠ Constructive dismissal

Hurt feelings ≠ Constructive dismissal

Constructive dismissal was incorporated into South African labour law in the 1980s and later codified in the Labour Relations Act 66 of 1995 (“LRA”). In terms of section 186(1)(e) of the LRA, an employee may resign, whether with or without notice, and claim unfair dismissal on the basis that their continued employment had become intolerable. Although the concept can be difficult to apply in practice, the Constitutional Court has clarified its meaning and reaffirmed its role within our law.

Sign up to our newsletter

Pin It on Pinterest